Facilities provided under Ease of Doing Business (EoDB)

Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Ltd has complied with the recommendations proposed under Business Reform Action Plan (BRAP) for Ease of Doing Business. The links related to the EoDB are provided below.

User can apply for New Service Connection, Load Change in Existing Connection using the Following Link

Currently there are three documents required for obtaining an electricity connection using Portal.

  1. ID Proof of the Applicant
  2. Letter of Authorization (in case of Company)
  3. Ownership proof of Premises

User can track their application using the Following Link

Tariff Details are available on our Portal and can be accessed using the following link.

Tariff Details

FCA /FPPAS Details are available on our Portal and can be accessed using the following link.

FCA /FPPAS Details

Electricity Duty information is available on our Portal and can be accessed using the following link.

Electricity Duty Details

Information related to planned future shutdowns and other previous interruptions can be viewed using the Following Link.

Permanent Connections

SnoTypeTimeline defined in PSGNo of Applications received onlineNo of Applications approvedNo of Applications pendingAverage time of resolutionMedian time of resolutionMinimum time taken for resolutionMaximum time taken for resolutionAverage Charges (INR)
1URBAN11 Days71710705355892 Days1 Days1 Days67 Days6500
2RURAL16 Days9549290280671 3 Days2 Days1 Days59 Days
8050

Temporary Connections

SnoTypeTimeline defined in PSGNo of Applications received onlineNo of Applications approvedNo of Applications pendingAverage time of resolutionMedian time of resolutionMinimum time taken for resolutionMaximum time taken for resolutionAverage Charges (INR)
1URBAN11 Days70226927592 Days2 Days1 Days50 Days9000
2RURAL16 Days36837364333172 Days2 Days1 Days87 Days
11000

Permanent Connections

S. No.Timeline defined in PSGTotal No. of applications received onlineTotal No. of applications approvedNo. of applications pendingAverage time of resolutionMinimum time taken for resolutionMedian time taken for resolutionMaximum time taken for resolutionAverage Cost (Excluding Extension Work and ME Cost)
17 Days46546503027 Rs.1616246

Temporary Connections

S. No.Timeline defined in PSGTotal No. of applications received onlineTotal No. of applications approvedNo. of applications pendingAverage time of resolutionMinimum time taken for resolutionMedian time taken for resolutionMaximum time taken for resolutionAverage Cost (Excluding Extension Work and ME Cost)
17 Days525203027 Rs.1839567

You can apply for DG Set Installation by Clicking Here

The charges for Name Transfer are as follows.

  1. LT Consumers – Rs. 170
  2. HT Consumers – Rs. 3360
s.noNo of application receivedNo of application processedAverage timeMinimum timeMaximum timeMedian
12188197250145

** The Data is updated on monthly basis and timelines are governed by public Lok Seva Guarantee Adhiniyam. For urban – 15 days & For Rural – 21 days