Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Ltd has complied with the recommendations proposed under Business Reform Action Plan (BRAP) for Ease of Doing Business. The links related to the EoDB are provided below.
Facilities provided under Ease of Doing Business (EoDB)
User can apply for New Service Connection, Load Change in Existing Connection using the Following Link
Currently there are three documents required for obtaining an electricity connection using Portal.
- ID Proof of the Applicant
- Letter of Authorization (in case of Company)
- Ownership proof of Premises
User can track their application using the Following Link
Tariff Details are available on our Portal and can be accessed using the following link.
Tariff DetailsFCA /FPPAS Details are available on our Portal and can be accessed using the following link.
FCA /FPPAS DetailsElectricity Duty information is available on our Portal and can be accessed using the following link.
Electricity Duty DetailsInformation related to planned future shutdowns and other previous interruptions can be viewed using the Following Link.
Permanent Connections
Sno | Type | Timeline defined in PSG | No of Applications received online | No of Applications approved | No of Applications pending | Average time of resolution | Median time of resolution | Minimum time taken for resolution | Maximum time taken for resolution | Average Charges (INR) |
---|---|---|---|---|---|---|---|---|---|---|
1 | URBAN | 11 Days | 71710 | 70535 | 589 | 2 Days | 1 Days | 1 Days | 67 Days | 6500 |
2 | RURAL | 16 Days | 95492 | 90280 | 671 | 3 Days | 2 Days | 1 Days | 59 Days | 8050 |
Temporary Connections
Sno | Type | Timeline defined in PSG | No of Applications received online | No of Applications approved | No of Applications pending | Average time of resolution | Median time of resolution | Minimum time taken for resolution | Maximum time taken for resolution | Average Charges (INR) |
---|---|---|---|---|---|---|---|---|---|---|
1 | URBAN | 11 Days | 7022 | 6927 | 59 | 2 Days | 2 Days | 1 Days | 50 Days | 9000 |
2 | RURAL | 16 Days | 36837 | 36433 | 317 | 2 Days | 2 Days | 1 Days | 87 Days | 11000 |
Permanent Connections
S. No. | Timeline defined in PSG | Total No. of applications received online | Total No. of applications approved | No. of applications pending | Average time of resolution | Minimum time taken for resolution | Median time taken for resolution | Maximum time taken for resolution | Average Cost (Excluding Extension Work and ME Cost) |
---|---|---|---|---|---|---|---|---|---|
1 | 7 Days | 465 | 465 | 0 | 3 | 0 | 2 | 7 | Rs.1616246 |
Temporary Connections
S. No. | Timeline defined in PSG | Total No. of applications received online | Total No. of applications approved | No. of applications pending | Average time of resolution | Minimum time taken for resolution | Median time taken for resolution | Maximum time taken for resolution | Average Cost (Excluding Extension Work and ME Cost) |
---|---|---|---|---|---|---|---|---|---|
1 | 7 Days | 52 | 52 | 0 | 3 | 0 | 2 | 7 | Rs.1839567 |
You can apply for DG Set Installation by Clicking Here
The charges for Name Transfer are as follows.
- LT Consumers – Rs. 170
- HT Consumers – Rs. 3360
s.no | No of application received | No of application processed | Average time | Minimum time | Maximum time | Median |
---|---|---|---|---|---|---|
1 | 2188 | 1972 | 5 | 0 | 14 | 5 |
** The Data is updated on monthly basis and timelines are governed by public Lok Seva Guarantee Adhiniyam. For urban – 15 days & For Rural – 21 days